This is a composite of a typical mineral processing plant deployment, not a single named client. The steps reflect how the system is installed and configured; the plant profile is illustrative.
The plant
A mid-sized processing plant runs two shifts, seven days a week. Its critical fixed plant includes a primary jaw crusher, three conveyors, a ball mill drive and four slurry pumps. Condition was checked by a monthly contractor survey and by artisans walking the plant. Most failures were found the way the gearbox in the first article of this series was: by the operator, after the line stopped.
The engineering manager's brief was simple: know about a change before it becomes a breakdown, and make sure every warning ends up as a job.
Weeks 1–2: decide what matters
The maintenance team ranked every machine by the cost of a failure, using the method from the second article in this series. Nine assets made the first cut. For each one they chose mounting points — bearing housings and gearbox casings — and confirmed each asset existed properly in the asset register, with a clear name and site.
One Zamatrack gateway was mounted centrally, connected to the plant network, and confirmed online.
Week 3: install and switch on
Twelve wireless sensors were paired with the gateway, each held close to it during installation and then mounted on its machine. Signal strength was checked at every mounting point before the team moved on.
Each sensor was set to report the measurements that mattered for its machine: vibration and temperature on every drive, a surface-temperature probe on the mill and crusher bearings, frequency-spectrum readings on the two highest-risk gearboxes, and tilt on the crusher base. Spectrum readings were set to every ten minutes rather than faster, because they use far more battery than anything else.
Weeks 3–4: register and attach
Every sensor was registered in Worxit by its serial number, copied exactly from the label, and attached to its asset. That last step matters: a sensor that isn't attached still records readings, but its alerts have nowhere to land.
Weeks 4–6: learn normal, then set limits
For two weeks nobody set a limit. The team watched the vibration and tilt trends in the Last data view to learn what each machine looked like on a normal shift, through start-ups, load changes and load-shedding restarts.
Then the maintenance engineer set the rules: an upper vibration limit per machine, a temperature limit per bearing, and a consecutive-readings count so a single spike on start-up wouldn't fire. Every sensor got an offline alert, using the recommended window Worxit worked out from its own reporting rhythm. Crusher and mill rules were set to High or Critical, with auto-create work order switched on.
What went wrong
Two things, both normal.
In week two, the planner reported that the sensors "looked two hours behind." They weren't. The planner's browser was set to the wrong time zone, so the server's receipt time and the sensor's own reading time appeared two hours apart. Once the browser was set to South African time, the gap dropped to the normal one or two minutes. Worxit shows both clocks deliberately, and it is worth explaining them to everyone on day one.
In week five, the first limits on two slurry pumps were set too tight and fired on every restart. The engineer raised the consecutive-readings count and adjusted the limit slightly, and the false alarms stopped without hiding real changes.
Weeks 7–12: tune and expand
With the first nine assets running cleanly, the team added sensors to the remaining conveyor drives and the second-tier pumps. The weekly planning meeting started with the Asset Faults list in Daily Operations rather than with last week's breakdowns.
The mirror
| What happened | |
|---|---|
| Before | A vibration change on a conveyor gearbox is heard by an artisan on night shift, mentioned on a WhatsApp group and forgotten. Nine days later the gearbox fails during peak production. |
| After | The same change crosses the engineer's limit three readings in a row. Worxit raises a High-priority vibration fault on that conveyor's asset record and creates a linked work order. The planner sees it in Daily Operations the next morning, orders the bearing, and the job is done in the Sunday shutdown. |
What to measure at 30, 90 and 180 days
| Milestone | What to measure |
|---|---|
| Day 30 | Critical assets with a sensor, a baseline and limits set |
| Day 90 | Faults raised by sensors and converted to planned work orders |
| Day 180 | Unplanned stoppage hours on monitored assets vs the same period last year |
Six lessons that apply to any plant
- Rank by consequence, not convenience. Put the first sensors where a failure costs most.
- Learn normal before you judge. Two weeks of baseline saves months of false alarms.
- Limits belong to your engineer. The software shows the shape; your team decides what is acceptable.
- Never let silence look healthy. Every sensor needs an offline alert.
- Make every warning a job. An alert that doesn't become a work order is just a notification.
- Explain the two clocks on day one. It saves a week of "the data looks wrong."
See it on your plant
Zamatrack supplies the gateway, the sensors and the Worxit software, with local support from one South African team. Software from R350 p/m ex VAT.
